144 .Smt. Vijila Sathyananth 
Will the Minister of SHIPPING be pleased to state :-
(a) whether it is a fact that more than 50 per cent of the
rail connectivity projects identified under Sagarmala,
are under implementation through various agencies;
(b) if so, the details thereof;
(c) whether it is also a fact that rail projects worth Rs.
18,800 crore being implemented, to reduce logistics
cost; and
(d) if so, the details thereof?
ANSWER ; 
(a) to (d) Yes Sir, there are 83 rail projects worth Rs. 56416.19 Crore identified under Sagarmala to be taken up by various agencies. Out of this, 51 projects are under implementation. Details of rail projects with status is attached.
List of rail projects under Sagarmala ;
S.No. Project Name Implementing Agency Stage Project Cost(in cr.) 1 Electrification of east yard revamped lines. 23.489 TKM Indian Railways Project Completed 20 2 Doubling of line from Rajatgarh to Barang Indian Railways Project Completed 380 3 Rail Connectivity to South Port of Krishnapatnam Port from Guduru Indian Railways Project Completed 300 4 Krishnapatnam-Venkatachalam – Doubling with electrification Indian Railways Project Completed 87 5 Decongesting RV line - 2nd line Raipur – Titlagarh -203 Km Indian Railways Under Implementation 758 6 3rd and 4th line from Budhapank- Salegaon via Rajatgarh Indian Railways Under Implementation 1173 7 Doubling of line from Sambalpur to Talcher Indian Railways Under Implementation 1112 8 Rail Obulavaripalle-Venkatachalam -95 km Indian Railways Project Completed 1825 9 Third line from Sukhinda Road to Jakhapura Indian Railways Under Implementation 56 10 New line from Jharsuguda to Barpalli Indian Railways Project Completed 1007 11 Bhadrachalam- Kovvuru New BG Line -151 Km Indian Railways Under Implementation 2154 12 Bhadrak – Nergundi 3rd Line Indian Railways Under Implementation 843 13 3rd line from Jakhapura to Haridaspur Indian Railways Project Completed 282 14 New Railway line bridge between Jajpur and Sukinda Road stations Indian Railways Project Completed 56 15 Upgradation of the track 10-12-14-16-18-19-20-21- 22 and 23 at EJC yard of KoPT Kolkata Port Trust Project Completed 47 16 Upgrade of existing rail network at Kolkata Dock System Kolkata Port Trust Project Completed 9 17 Railway line between Marshalling Yard and Hare Island V. O. Chidambaranar Port Trust Project Completed 98 18 Railway line at west of western yard 1 –earlier common rail yard and providing paving block platform in between new track and western yard I – Chennai Chennai Port Trust Project Completed 14 19 Providing a direct connection between OEC and Western Sector jointing at NAD Curve from E.Co. Rly. Visakhapatnam Port Trust Under Implementation 22 20 Connection of dead end line at North of RandD yard to Eastern Grid –Third line from E.Co.Rlys. Visakhapatnam Port Trust Under Implementation 24 21 Upgradation of platform no. 2 and 3 in the Port Marshalling Yard at NMPT New Mangalore Port Trust Project Completed 5 22 Upgradation of Railway line 1 and 2 at NMPT New Mangalore Port Trust Project Completed 5 23 3rd line rail onnectivity from Jasai to JNPT Jawaharlal Nehru Port Trust Under Implementation 126 24 JNPT Part I Development of DFC compliant Common Rail YardJNPT Part II Development of DFC compliant Common Rail Yard; Modification to ROB Jawaharlal Nehru Port Trust Under Implementation 267 25 Rail connectivity to berth No. 13- 14- 15 and 16 from take-off point to west end of berth at Kandla Port. Deendayal Port Trust Project Completed 109 26 Rail Connectivity to 4th Terminal being developed by BMCTPL –PSA Jawaharlal Nehru Port Trust Project Completed 50 27 2nd Railway Line from Durgachak take off point to ‘A’ cabin at Durgachak at HDC Haldia Dock Complex Under Implementation 75 28 Extension of line No. 11 to 15 to full length at RandD yard. Visakhapatnam Port Trust Under Tendering 18 29 Last mile rail connectivity to Enayam Port in Kanyakumari district Enayam Port DPR Preparation 300 30 Northern Rail Link connecting north of Minjur to KPL Kamarajar Port Limited DPR Preparation 300 31 Rail Connectivty to Belekeri Port Belekeri Port DPR Preparation 400 32 Augmentation-doubling of southern rail connectivity to KPL Kamarajar Port Limited Under Implementation 60 33 Full rake wagon handling line with paving 30m wide at Mormugao Mormugao Port Trust Project Completed 18 34 Providing Signalling and Telecommunication system for Railway Network at Mormugao Port Mormugao Port Trust Project Completed 14 35 Vishnupuram- Mellacheruvu New BG line Indian Railways Project Completed 378 36 Doubling of line Vijaywada-Gudivada- Bhimavaram-Narasapur- Gudivada-Machlipatnam and Bhimavaram-Nidadavolu -221 km Indian Railways Under Implementation 1504 37 Various Signalling works at VPT Visakhapatnam Port Trust Submit Proposal 24 38 Upgrading to accommodate full rake length at 7 Netaji Subash Dock and its yard under KDS- KoPT Kolkata Port Trust Project Completed 16.5 39 Banspani-Daitari-Tomka-Jakhapura Indian Railways Under Implementation 943 40 Kirandul-Jagdalpur Indian Railways Under Implementation 1161 41 Jagdalpur-Koraput doubling Indian Railways Under Implementation 1547 42 Vizianagram-Titlagarh (sambalpur) Indian Railways Under Implementation 2336 43 3rd &4th line between Jarapaada – Budhapank with flyover at Talcher Indian Railways Under Implementation 810 44 3rd line in balance section between Bhadra – Vizanagagram Indian Railways Under Implementation 728 45 Kottavalasa-Jagdalpur(Koraput) Indian Railways Under Implementation 2500 46 Koraput-Singapur Road. Indian Railways Under Implementation 2362 47 Panskura –Kharagpur 3rd line (44.7km) with new MM for Panskura – Ghatal (32.8km) New line Indian Railways Under Implementation 426 48 Kharagpur – Narayangarh 3rd line Indian Railways Under Implementation 291 49 Chennai Beach-Attipattu 4th line Indian Railways Under Implementation 258 50 Chennai Beach – Korukkupet 3rd line Indian Railways Project Completed 168 51 Madurai-Maniyachi-V. O . Chidambaranar doubling Indian Railways Under Implementation 1182 52 Netravati-Mangalore Indian Railways Under Implementation 28 53 Chenganur – Chingavanam Indian Railways Project Completed 436 54 Kankanadi-Panambur Patch doubling Indian Railways Under Implementation 238 55 Kurruppanthara-Chingavanam Indian Railways Under Implementation 457 56 Ambalapuzha-Haripad Indian Railways Under Implementation 289 57 Ernakulam-Kumbalam Patch doubling Indian Railways Under Implementation 189 58 Kumbalam-Thuravur Patch doubling Indian Railways Under Implementation 253 59 Viramgam-Samakhiali (182.23km) epc between Sukhpur – Samakhali (125km) (2011-12) Indian Railways Under Implementation 1037.16 60 Palanpur-Samakhayali n(KRCL) Indian Railways Under Implementation 1548.66 61 Surendranagar-Rajkot-doubling of broad gauge single line section Indian Railways Under Implementation 1002.39 62 Talcher-Bimlagarh Indian Railways Under Implementation 1928.07 63 Kakinada – Pithapuram Indian Railways Under Implementation 220 64 Gudur-Durgarajapatnam Indian Railways Under Implementation 761.37 65 Chennai-Cuddalore via Mahabalipuram Indian Railways Under Implementation 2300 66 Madurai-V. O . Chidambaranar via Aruppukkottai Indian Railways Under Implementation 1800 67 Mayiladuturai-Tiruvarur-Karaikudi & Tiruturaipundi- Agastiyampalli (223.69km) restoration of Needamangalam- Mannargudi line (13.25km) & Mannargudi-Pattukkottai (41km) with Thanjavur-Pattukottai (47.20km) Indian Railways Under Implementation 2072 68 Tiruchchirapalli – Nagore – Karaikal (145.33km) with extra. Nagapattinam – Velankani – Tiruturaipundi (43kms including new MM Karaikudi – Paralam New Line (23km) Indian Railways Under Implementation 980 69 Patan – Bhildi new line part of Bhildi – Viramgam (157km) with new MM for Mehsana – Taranga Hill (57.4km) gauge conversion Indian Railways Under Implementation 598 70 Rajkot-Veraval, Wansjalia to Jetalsar with new MM for Shapur – Saradiya (46km) & Somnath –Kodinar (36.91km) Indian Railways Under Implementation 1329 71 Bhuj-Naliya (101.35km) with extn. From Naliya to Vayor (24.65km) Indian Railways Under Implementation 484 72 Providing Railway Double line track (Twin Single Line) between Holding Yard –I and Kamarajar Port, Alteration of existing Electronic Interlocking Kamarajar Port Limited Project Completed 7.23 73 Doubling of line from Titlagarh to Sambalpur Indian Railways Under Implementation 948 74 New Line from Angul to Sukhinda Indian Railways Under Implementation 1203 75 New Line from Haridaspur to Paradip Indian Railways Under Implementation 1845 76 Rail line Hospet-Hubli-Londa-Tinaighat-Vasco da Gama -352.28 km including Vasco-Madgaon-Kulem-Castle Rock Section Indian Railways Under Implementation 2127 77 Electrification of VPT railway lines 45.143 TKM Visakhapatnam Port Trust DPR Preparation 20 78 Kotipalli- Narsapur New BG Line -57.21 Km Indian Railways Under Implementation 2120 79 Barithengarh-Ratnagiri chord rail line to haridaspur-paradip main line Paradip Port Trust Under Tendering 670 80 Direct connectivity to Mindi Yard from E.Co. Railways- SC Railways Visakhapatnam Port Trust DPR Preparation 45 81 Rail Connectivity to Azhikkal port Azhikkal Port DPR Preparation 600 82 Dedicated goods line between Wadala and Kurla for freight movement from MbPT Mumbai Port Trust Under Implementation 176.81 83 Development of Rail Connectivity for BOT berths at Paradip [JSW is implementing the project] Paradip Port Trust Under Implementation 55
 
Onetamil News ad
 
 
 
 

தொடர்புடைய செய்திகள்

 

Onetamil News

Onetamil News
 
Onetamil News
 
Onetamil News Birthday Wishes
 

இத படிங்க முதல்ல

விளம்பரங்கள்

Onetamil News Onetamil News
Onetamil News Logo